Transformer Technologies™ One Power Solution
ONE POWER SOLUTION

Featured Success Story

San Diego Gas & Electric

Utilizing our affiliate company, TCI of Alabama, Transformer Technologies successfully removed equipment from 5 separate substations in Southern California. Two substations required removal of transformers, circuit breakers, lattice towers and auxilliary equipment; Two substations required removal of untested bushings; and One substation required removal of two large transformers. Transformer Technologies arranged the Hazardous Material hauling and worked with TCI of Alabama to test and process the bushings. All transportation, crane work, and demolition was coordinated to minimize substation disruption and fit the customer's schedule.

Success Stories By Client Type

Public Utility Districts »
Investor Owned Utilities »
Government Facilities »
Hydro-Electric Plants »
Large Scale Demolition »
Industrial Facilities »

Latest Success Stories

Mossy Rock Dam

To make way for new units, Tacoma Power needed to remove three single phase transformers and related iso-bus. Transformer Technologies pulled the bushings and removed the radiators to prepare the units for movement. We contracted an equipment mover to jack & rolled the units off the transformer deck. Each transformer was further downsized prior to hauling to Salem for final destruction.

GWP - Howard Substation
Glendale, CA

Transformer Technologies was contracted by Glendale Water & Power to remove three 35,000 pound transformers from their Howard Substation in downtown Glendale. The logisitcs made this job interesting! The substation was surrounded by a 25' wall and was located in a busy area of the city. Transformer Technologies arranged for the oil removal, crane service, and transportation to have minimal impact on the City. The lifts went smoothly and closure of a portion of the street was held to a short timeframe.

Avista - Sandpoint

Avista needed to clear a decomissioned substation in Sandpoint, Idaho. Transformer Technologies was hired to remove all transformers, regulators, and OCB's, take down all overhead structures, and clean all material down to the concrete footings. Transformer Technologies provided the work crew, arranged for the crane, and coordinated all transportation. The complete job took less than one week and was performed to the highest environmental and safety standards.

BPA - Ross Substation

Transformer Technologies was awarded a project to dismantle a large transformer inside a live Bonneville Power Substation. Prior to starting, a detailed Site Specific Safety Plan was submitted and approved. Work progressed as planned, with no environmental or safety occurrences. Our field crew received commendation from BPA for efficiency and attention to detail.

Hawaii

Transformer Technologies solved a difficult problem for HECO by performing an On-Site teardown of a 200,000 pound transformer. Since the cost to load, move, and ship such a large unit was extremely high, we offered to send a crew from Oregon. HECO was skeptical, as the last contractor did not perform to acceptable environmental standards. Working with Haztech Environmental Services, Transformer Technologies visited the site in advance and submitted a detailed environmental plan. The transformer dismantling proceeded without incident, on time, and under budget. Savings to HECO exceeded $50,000!

PacifiCorp Hornbrook

Transformer Technologies was presented with a unique opportunity - remove three large single phase transformers from an environmentally sensitive area of a hydro electric facility, only accessible via a severely load limited bridge. Our solution was to dismantle the units in place, significantly downsize all material, and shuttle the material across the bridge - No cranes or large trailers were required. All work was performed to the customer's satisfaction, while still providing positive revenue.

4709 Turner Road SE, Salem OR 97317 | Ph: (503) 364-5476 | Fax: (503) 364-3339